Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?

A.
'Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change'.
Answers
A.
'Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change'.
B.
'Enable altering of planned date for task in WIP/Closed'.
Answers
B.
'Enable altering of planned date for task in WIP/Closed'.
C.
'Rollup project start date from tasks'.
Answers
C.
'Rollup project start date from tasks'.
D.
'Calculate ROI percentage based on a project's estimated cost and its net value'.
Answers
D.
'Calculate ROI percentage based on a project's estimated cost and its net value'.
Suggested answer: A

Explanation:

According to the ServiceNow documentation1, this property controls whether the start dates of the resource plan, cost plan, and benefit plan are automatically updated when the start date of the demand or project is changed. If this property is set to true, then the plans will be shifted by the same number of days as the demand or project start date change. If this property is set to false, then the plans will not be affected by the demand or project start date change.

1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/reference/r_Properties.html