A project expense line is cost associated with a specific source, except for:

A.
Fixed Assets.
Answers
A.
Fixed Assets.
B.
Program.
Answers
B.
Program.
C.
Resource.
Answers
C.
Resource.
D.
Software.
Answers
D.
Software.
Suggested answer: B

Explanation:

According to theProject Expense Linesdocument, a project expense line is cost associated with a specific source, such as fixed assets, resource, or software. The program field on the project expense line form is not a source of cost, but a reference to the program that the project belongs to. Therefore, the correct answer is B. Program. The other options are not correct, as they are sources of cost for a project expense line.