The Project management application supports two types of external dependencies. What are they?

Choose 2 answers

A.
Hard Dependency.
Answers
A.
Hard Dependency.
B.
Task Dependency.
Answers
B.
Task Dependency.
C.
Change Dependency.
Answers
C.
Change Dependency.
D.
Soft Dependency.
Answers
D.
Soft Dependency.
E.
Milestone Dependency.
Answers
E.
Milestone Dependency.
Suggested answer: A, D

Explanation:

The Project Management application supports two types of external dependencies: hard dependency and soft dependency. A hard dependency is a dependency that must be met before a task can start or finish. A soft dependency is a dependency that is preferred but not mandatory for a task to start or finish. You can find more information about these dependency types in theProduct Documentationfor ServiceNow.