Upon completion of a project a Belt must complete the Documentation Plan then transfer responsibility for this to the ____________________.

A.
Project Review Committee
Answers
A.
Project Review Committee
B.
Division Manager
Answers
B.
Division Manager
C.
Sales Team
Answers
C.
Sales Team
D.
Process Owner
Answers
D.
Process Owner
Suggested answer: D