What are three requirements of the Vblock System test plan? (Choose three.)

A.
All tests identified in the test plan must be executed.
Answers
A.
All tests identified in the test plan must be executed.
B.
Observed results must be documented by a VCE certified resource.
Answers
B.
Observed results must be documented by a VCE certified resource.
C.
Tests are confidential and must not be performed in view of the customer.
Answers
C.
Tests are confidential and must not be performed in view of the customer.
D.
Once tests are completed, the customer must sign the test plan document.
Answers
D.
Once tests are completed, the customer must sign the test plan document.
E.
A completed test plan must be submitted to the VCE project manager.
Answers
E.
A completed test plan must be submitted to the VCE project manager.
Suggested answer: B, D, E