What are two expected results of the VMware vMotion test plan conducted by VCE at the completion of a Vblock System build? (Choose two.)
A.
No unexpected errors or faults occur.
B.
The secondary VSM takes over from the primary VSM.
C.
There will be minimal packet loss during vMotion.
D.
Traffic fails over to the redundant port channel each time a port-channel is disabled.