While preparing for a new four-node cluster installation, the consultant has a Tech Review Call with the customer. The hardware is as follows:

* 4 nodes in 1 Block

* 8 x 10 GbE Ports

* 4 x 1 GbE IPMI Ports

* Adequate Ethernet ports are available

* Ethernet cables are correct and available

* Adequate rack space is available

Which remaining item must be confirmed as available onsite?

A.
Crash Cart
Answers
A.
Crash Cart
B.
Fibre Channel switches
Answers
B.
Fibre Channel switches
C.
Redundant 208v power
Answers
C.
Redundant 208v power
D.
Redundant 110v power
Answers
D.
Redundant 110v power
Suggested answer: C