A consultant successfully completes a Foundation using a flat switch. The consultant then works with the customer to move the cluster over to their production network. After the move, the CVMs and hypervisors can no longer communicate, which prevents the cluster from starting.

Which option should be used to resolve this issue?

A.
If the IPMI is in use, check that the IPMI can ping the default gateway over IPv6.
Answers
A.
If the IPMI is in use, check that the IPMI can ping the default gateway over IPv6.
B.
Make sure that the IPMI and CVM VLAN is manually tagged on the Host and CVM.
Answers
B.
Make sure that the IPMI and CVM VLAN is manually tagged on the Host and CVM.
C.
Verify that IPv6 Link Local and DHCP is enabled on all switch ports.
Answers
C.
Verify that IPv6 Link Local and DHCP is enabled on all switch ports.
D.
If using VLANs, confirm the hypervisor/CVM VLAN is set as Native on the switch ports.
Answers
D.
If using VLANs, confirm the hypervisor/CVM VLAN is set as Native on the switch ports.
Suggested answer: D