On which types of objects can time be recorded in Workfront?

A.
Tasks. Timesheets and Documents
Answers
A.
Tasks. Timesheets and Documents
B.
Portfolios, Tasks and Issues
Answers
B.
Portfolios, Tasks and Issues
C.
Projects. Tasks and Issues
Answers
C.
Projects. Tasks and Issues
Suggested answer: C

Explanation:

In Adobe Workfront, time can be recorded on Projects, Tasks, and Issues. This flexibility allows users to track time spent on various types of work items, providing comprehensive time management and reporting capabilities.

Record Time on Projects:

Navigate to a project.

Click on the 'Hours' tab.

Enter the time spent on the project.

Record Time on Tasks:

Navigate to a task within a project.

Click on the 'Hours' tab.

Enter the time spent on the task.

Record Time on Issues:

Navigate to an issue within a project.

Click on the 'Hours' tab.

Enter the time spent on the issue.

The processes for recording time on various objects are detailed in the Workfront time-tracking documentation and training materials (Advanced Reporting - Monique Evans - Code Snippet - June 2, 2020).