Question 3 - AD0-E908 discussion

Report
Export

A project manager is reviewing an issue with a document attached The manager notices that the issue is connected to the wrong project What will happen to the document when the issue is moved to the correct project?

A.
The document is copied to the new issue, leaving the original on the project.
Answers
A.
The document is copied to the new issue, leaving the original on the project.
B.
The document and any approvals associated with the document will move along with the new issue.
Answers
B.
The document and any approvals associated with the document will move along with the new issue.
C.
The document will not move to the new issue.
Answers
C.
The document will not move to the new issue.
Suggested answer: B

Explanation:

When an issue with a document attached is moved to a different project in Adobe Workfront, the document and any approvals associated with it will also move to the new project along with the issue. This ensures that all related information and approvals are retained and correctly associated with the issue in its new context.

Move the Issue:

Navigate to the issue that needs to be moved.

Select the option to move the issue to another project.

Verify Document Movement:

After moving the issue, check the new project to ensure the document is correctly associated with the issue.

Verify that any approvals linked to the document are also moved and remain intact.

This behavior is confirmed in the Workfront documentation and issue management training guides, which explain how documents and approvals are handled when moving issues (Workfront Training Deck - Worker 2.15.23).

asked 02/10/2024
MOHAMED RIAZ MOHAMED IBRAHIM
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first