What does the Cost Performance Index (CPI) of a project in Workfront track?

A.
Relationship between the planned and actual cost
Answers
A.
Relationship between the planned and actual cost
B.
Difference between the planned benefit and budgeted cost
Answers
B.
Difference between the planned benefit and budgeted cost
C.
Total expected value after calculating its benefit and removing the costs
Answers
C.
Total expected value after calculating its benefit and removing the costs
Suggested answer: A

Explanation:

The CPI measures the cost efficiency of budgeted resources on a project. It is calculated by dividing the earned value (EV) by the actual cost (AC). A CPI value greater than 1 indicates that the project is under budget.