Question 26 - AD0-E908 discussion

Report
Export

A project manager is using information in the Portfolio Optimizer to analyze which projects to prioritize. Where is this information coming from?

A.
The project's Alignment Score
Answers
A.
The project's Alignment Score
B.
The project's Baseline
Answers
B.
The project's Baseline
C.
The project's Business Case
Answers
C.
The project's Business Case
Suggested answer: A

Explanation:

The Portfolio Optimizer in Adobe Workfront is a tool used by project managers and portfolio managers to analyze and prioritize projects. The information used in the Portfolio Optimizer primarily comes from the project's Alignment Score. This score is a calculated metric that reflects how well a project aligns with the strategic goals and priorities of the organization. The Alignment Score helps in objectively comparing and prioritizing projects based on their strategic value.