Question 28 - AD0-E908 discussion
A project manager wants to use Portfolios and Programs to organize projects. What two considerations would apply when using these objects? (Choose two.)
A.
Projects can be associated with a multiple Programs and Portfolios
B.
Programs are containers for Portfolios
C.
Portfolios are containers for Programs
D.
Projects must be assigned to a Program before they can be associated with a Portfolio
E.
Projects can be associated with only one Program or Portfolio