Aside from predecessors, resource manager assignments, and system administrator settings, what are three prerequisites for using the Resource Planner and Workload Balancer? (Choose three.)

A.
Job Roles assigned to Tasks
Answers
A.
Job Roles assigned to Tasks
B.
Task Planned Hours greater than zero
Answers
B.
Task Planned Hours greater than zero
C.
Task Durations greater than zero
Answers
C.
Task Durations greater than zero
D.
Schedules added to templates
Answers
D.
Schedules added to templates
E.
Time off logged in User Schedules
Answers
E.
Time off logged in User Schedules
Suggested answer: A, B, C

Explanation:

Objective: Identify prerequisites for using the Resource Planner and Workload Balancer.

Prerequisites:

Prerequisite 1: Job Roles assigned to Tasks

Prerequisite 2: Task Planned Hours greater than zero

Prerequisite 3: Task Durations greater than zero