A server room contains ten physical servers that are running applications and a cluster of three dedicated hypervisors. The hypervisors are new and only have 10% utilization. The Chief Financial Officer has asked that the IT department do what it can to cut back on power consumption and maintenance costs in the data center. Which of the following would address the request with minimal server downtime?
A.
Unplug the power cables from the redundant power supplies, leaving just the minimum required.
B.
Convert the physical servers to the hypervisors and retire the ten servers.
C.
Reimage the physical servers and retire all ten servers after the migration is complete.
D.
Convert the ten servers to power-efficient core editions.