SAP C_ACT_2403 Practice Test 2

Question 1 / 40
Which of the following best outlines the sequence of testing in the Realize phase?
Data Migration String Test User Acceptance Test
String Test Integration Test User Acceptance Test
String Test User Acceptance Test Integration Test
Integration Test User Acceptance Test String Test
Comment (0)
Suggested answer: B
Explanation:
The typical sequence of testing in the Realize phase begins with the String Test, followed by the Integration Test to validate cross-functional flows, and concludes with the User Acceptance Test (UAT) to confirm system readiness from an end-user perspective.