Question 1

Report
Export
Collapse

Which of the following activities take place during the Discover phase in an SAP BW/4HANA implementation? Note: There are 2 correct answers to this question.

Create, review, and sign off the Project Charter.

Create, review, and sign off the Project Charter.

Discuss the benefits and functionality of SAP Analytics Cloud.

Discuss the benefits and functionality of SAP Analytics Cloud.

Create, review, and sign off the Project Management Plan.

Create, review, and sign off the Project Management Plan.

Discuss the benefits of SAP Data Warehouse Cloud.

Discuss the benefits of SAP Data Warehouse Cloud.

Suggested answer: B, D

Explanation:

In the Discover phase of an SAP BW/4HANA implementation, high-level discussions on the benefits of related tools like SAP Analytics Cloud and SAP Data Warehouse Cloud take place. This phase focuses on exploring and understanding available functionalities to inform decision-making.

asked 19/11/2024
JP Pelovello
48 questions

Question 2

Report
Export
Collapse

When conducting an upgrade of an SAP S/4HANA Cloud, public edition three-system landscape, in which phase are the Business Roles updated?

Explore

Explore

Deploy

Deploy

Discover

Discover

Realize

Realize

Suggested answer: D

Explanation:

During the Realize phase, Business Roles are updated to align with the upgraded solution's requirements and configurations. This ensures that the roles meet both security and functional needs in the updated environment.

asked 19/11/2024
Ervin Loong
45 questions

Question 3

Report
Export
Collapse

You are transitioning to SAP S/4HAN

In which phase do you adjust custom code?

In which phase do you adjust custom code?

Realize

Realize

Deploy

Deploy

Explore

Explore

Prepare

Prepare

Suggested answer: A

Explanation:

Custom code adjustments are typically made in the Realize phase, where the system configuration and development activities take place. This phase involves adapting custom code to align with SAP S/4HANA's updated architecture and functionalities.

asked 19/11/2024
nico farina
38 questions

Question 4

Report
Export
Collapse

In which phase do you collect the main functional attributes of the product as per the Agile definition?

Discover

Discover

Prepare

Prepare

Explore

Explore

Realize

Realize

Suggested answer: C

Explanation:

In SAP Activate's Agile Project Planning, the Explore phase is when teams refine and capture the main functional attributes of the product, often through user stories and requirements workshops. This phase allows teams to iteratively understand, document, and confirm the main attributes before moving to realization.

asked 19/11/2024
Michael Bodine
28 questions

Question 5

Report
Export
Collapse

What information does the project team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct answers to this question.

Available project resources

Available project resources

Definition of Ready

Definition of Ready

Definition of Done

Definition of Done

Benchmark user story

Benchmark user story

Suggested answer: B, C

Explanation:

The 'Definition of Ready' (DoR) ensures that user stories meet predefined criteria before estimation, while the 'Definition of Done' (DoD) clarifies the completion standards. Both definitions support accurate estimations by establishing clear, mutual expectations for user stories.

asked 19/11/2024
Eduardo Lapuente
42 questions

Question 6

Report
Export
Collapse

Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity

Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity

Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team

Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team

Product Owner's relative effort estimate that will be needed to implement and test the user story

Product Owner's relative effort estimate that will be needed to implement and test the user story

Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks

Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks

Suggested answer: A

Explanation:

In Agile practices within SAP Activate, estimation is often conducted using 'story points' to evaluate relative size and complexity. A top-down approach led by the Scrum Master ensures that all aspects of story complexity are considered, facilitating accurate, consensus-driven estimates.

asked 19/11/2024
Ash Eller
37 questions

Question 7

Report
Export
Collapse

What is Scrum of Scrums?

Inspection of code and configuration prior to sprint demo

Inspection of code and configuration prior to sprint demo

Integration meeting among the various Scrum teams

Integration meeting among the various Scrum teams

Scrum team led by very experienced Scrum master

Scrum team led by very experienced Scrum master

Alternative to regular Scrum process for a very large team

Alternative to regular Scrum process for a very large team

Suggested answer: B

Explanation:

The Scrum of Scrums is a cross-team coordination meeting, allowing teams working on interconnected deliverables to synchronize efforts, address dependencies, and manage impediments. This approach is beneficial for large projects requiring multiple Scrum teams.

asked 19/11/2024
Preety Koul
39 questions

Question 8

Report
Export
Collapse

What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question.

Estimate the backlog user stories.

Estimate the backlog user stories.

Define objectives for each release.

Define objectives for each release.

Analyze the functional and technical dependencies between user stories.

Analyze the functional and technical dependencies between user stories.

Prioritize backlog user stories by business priority.

Prioritize backlog user stories by business priority.

Suggested answer: B, D

Explanation:

The product owner's responsibilities include defining objectives for each release to align with business goals and prioritizing backlog items by business priority to ensure high-value deliverables are completed first. While the team estimates user stories, the product owner ensures clarity and prioritization.

asked 19/11/2024
Garwin Liu
36 questions

Question 9

Report
Export
Collapse

Which activity helps the project team identify and add user stories to the backlog?

Assessing documentation requirements

Assessing documentation requirements

Benchmarking current business processes

Benchmarking current business processes

Planning the release and sprints

Planning the release and sprints

Conducting the fit-to-standard workshop

Conducting the fit-to-standard workshop

Suggested answer: D

Explanation:

The fit-to-standard workshop is a key activity in SAP Activate that involves aligning SAP standard processes with business requirements. During this workshop, the team identifies gaps and additional requirements, which are then translated into user stories and added to the backlog for implementation.

asked 19/11/2024
Ankur Patel
42 questions

Question 10

Report
Export
Collapse

When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?

Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.

Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.

Realize phase scope, planning, and budget should be completed and final.

Realize phase scope, planning, and budget should be completed and final.

User stories on the product backlog should be in a ready state for the first 2 to 3 sprints.

User stories on the product backlog should be in a ready state for the first 2 to 3 sprints.

Release plan and sprint ceremony guidelines should be finalized.

Release plan and sprint ceremony guidelines should be finalized.

Suggested answer: A

Explanation:

At the start of the Realize phase, basic sprint planning and duration for the first few sprints should be established to ensure a smooth start. This approach supports incremental development by setting priorities and defining the immediate tasks for the project team.