Which of the following activities take place during the Discover phase in an SAP BW/4HANA implementation? Note: There are 2 correct answers to this question.
Create, review, and sign off the Project Charter.
Discuss the benefits and functionality of SAP Analytics Cloud.
Create, review, and sign off the Project Management Plan.
Discuss the benefits of SAP Data Warehouse Cloud.
When conducting an upgrade of an SAP S/4HANA Cloud, public edition three-system landscape, in which phase are the Business Roles updated?
Explore
Deploy
Discover
Realize
You are transitioning to SAP S/4HAN
In which phase do you adjust custom code?
Realize
Deploy
Explore
Prepare
In which phase do you collect the main functional attributes of the product as per the Agile definition?
Discover
Prepare
Explore
Realize
What information does the project team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct answers to this question.
Available project resources
Definition of Ready
Definition of Done
Benchmark user story
Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?
Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity
Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team
Product Owner's relative effort estimate that will be needed to implement and test the user story
Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks
What is Scrum of Scrums?
Inspection of code and configuration prior to sprint demo
Integration meeting among the various Scrum teams
Scrum team led by very experienced Scrum master
Alternative to regular Scrum process for a very large team
What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question.
Estimate the backlog user stories.
Define objectives for each release.
Analyze the functional and technical dependencies between user stories.
Prioritize backlog user stories by business priority.
Which activity helps the project team identify and add user stories to the backlog?
Assessing documentation requirements
Benchmarking current business processes
Planning the release and sprints
Conducting the fit-to-standard workshop
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
Realize phase scope, planning, and budget should be completed and final.
User stories on the product backlog should be in a ready state for the first 2 to 3 sprints.
Release plan and sprint ceremony guidelines should be finalized.