SAP C_ACT_2403 Practice Test - Questions Answers, Page 3
List of questions
Question 21
What activity do you perform during the daily stand-up meeting?
Question 22
What criteria does the product owner use to sequence the backlog? Note: There are 2 correct answers to this question.
Question 23
Who determines the tasks that are required to complete the committed backlog items in a Sprint?
Question 24
What is the purpose of the scrum board?
Question 25
When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
Question 26
What is the objective of using scaling Scrum techniques when coordinating large teams in complex projects?
Question 27
How do you set up Scrum teams? Note: There are 2 correct answers to this question.
Question 28
According to the Definition of Done, which activity must be completed for each Sprint?
Question 29
What do you do during the sprint retrospective meeting?
Question 30
Which of the following is a key characteristic of the Agile project approach?
Question