A Scrum board contains issues from a single project. An extract of the project's permission scheme is shown.
Who can definitely see the Scrurn board and rank issues?
All projects use a shared permission scheme.
The Browse Projects permission needs to be updated so that project administrators can manage access to their own projects.
What entry must be added to the Browse Projects permission?
You are a project administrator of DEV. Omar is a Jira administrator.
Identify two project settings that Omar can update in DEV but you cannot. (Choose two.)
Explanation:
As a project administrator of DEV, you can update some project settings such as project shortcuts, description, name, and versions. However, you cannot update the notification scheme or the key of the project, as these are global settings that require Jira administrator permissions. Therefore, the correct answer is A and C.Reference:Managing project permissions,Managing project notifications,Changing the project key
Savresh can create issues and assign them to anyone in the Testers group. However, they cannot re-assign issues to Savresh. What are two possible reasons for this? (Choose two.)
Anu has access to the DEV project and its Scrum board.
She also needs to plan, start, and complete sprints, and to edit sprint goals and dates
Where must Anu be added onto?
Bob can see only 20 out of 50 issues in a particular scrum project.
Browse Projects permission is granted to a single group. What does Bob need to see all the issues?
The ''Open issues filter of your project shows bugs, along with epics and stones.
You then view the project's Scrum board where you only see epics and stories but not bugs.
Which configuration is responsible for this behavior?
Which statement is definitely true about priorities in Jira?
A Scrum team working on multiple epics complains that they are constantly being pushed to complete more work than they think can be completed. Apparently, the product owner has constantly overloaded each of the past 8 sprints. Which single report can instantly prove their statement?
Your team uses a custom field of type Labels to track keywords associated with incoming requests. Issues can have multiple keywords, and new keywords can be added at any time. They want to see keywords displayed prominently when viewing all cards on a board. Which configuration meets this need?
Explanation:
The best configuration to meet the team's need of displaying keywords prominently when viewing all cards on a board is card layout. Card layout allows you to customize what fields are shown on each card on a board, and you can choose to show any custom field of type Labels on the cards. Swimlanes are used to group issues into horizontal lanes based on certain criteria, such as assignee, priority, or query, but they do not show labels on each card. Card colours are used to highlight issues based on certain attributes, such as issue type, priority, or query, but they do not show labels on each card either. Issue detail view is used to show more information about an issue when you select it on a board, but it does not affect how cards are displayed on the board. Therefore, the correct answer is A.Reference: [Configuring card layout], [Configuring swimlanes], [Configuring card colours], [Using boards]
Question