ExamGecko
Home / Blue Prism / APD01 / List of questions
Ask Question

Blue Prism APD01 Practice Test - Questions Answers, Page 2

Question list
Search

List of questions

Search

Related questions











Question 11

Report
Export
Collapse

A PDD has been created which includes a requirement to log in to an application called CDS. The CDS application only allows a user account to be logged into the application on one machine at a time. The client wishes to hold the credentials for logging into CDS in the Blue Prism Credential store. It has been calculated that the automated solution will require 3 resource PC's to enable the case volume to be worked within SLA's. Which is the most appropriate design decision to accommodate the above requirements?

Create user accounts and sets of Credentials per Resource PC in the Blue Prism Credential Manager for the CDS Application.
Create user accounts and sets of Credentials per Resource PC in the Blue Prism Credential Manager for the CDS Application.
Ask IT to enable concurrent logins to the CDS application for Blue Prism User Accounts
Ask IT to enable concurrent logins to the CDS application for Blue Prism User Accounts
Login in to the CDS application manually and let Blue Prism take over once the login is complete
Login in to the CDS application manually and let Blue Prism take over once the login is complete
Create a single Credential in the Blue Prism Credential Manager for the CDS Application. Use a Blue Prism Environment Lock to ensure that only one Resource PC can be logged in to the CDS application at a time
Create a single Credential in the Blue Prism Credential Manager for the CDS Application. Use a Blue Prism Environment Lock to ensure that only one Resource PC can be logged in to the CDS application at a time
Suggested answer: D

Explanation:

Reference: https://dotnetbasic.com/2019/04/blue-prism-credential-manager.html

asked 16/09/2024
Carlotta Agape
39 questions

Question 12

Report
Export
Collapse

Which of the following statements regarding Blue Prism Credentials are true?

The Business Object; Internal - Credentials cannot retrieve encrypted credentials from the Blue Prism database 2. It is best practice to hold application credentials within the Process that requires them
The Business Object; Internal - Credentials cannot retrieve encrypted credentials from the Blue Prism database 2. It is best practice to hold application credentials within the Process that requires them
It is best practice to hold application credentials within the Object that requires them
It is best practice to hold application credentials within the Object that requires them
It is possible to hold Blue Prism Credentials in an unencrypted state
It is possible to hold Blue Prism Credentials in an unencrypted state
1 only
1 only
2 only
2 only
3 and 4
3 and 4
None
None
Suggested answer: D
asked 16/09/2024
Simon Merlin AGHOKENG
39 questions

Question 13

Report
Export
Collapse

A business requirement exists to be able to distinguish between cases that have failed due to 'not being an adult' and cases that have failed due to 'invalid ID' based on the exception detail Blue Prism has captured. The following Process configuration has been built as a solution.

Blue Prism APD01 image Question 13 20693 09162024192515000000

Which of the following statements are correct?

The Process configuration will meet the requirements
The Process configuration will meet the requirements
The Process will fail because 2 Recover stages lead to a single Resume stage
The Process will fail because 2 Recover stages lead to a single Resume stage
The Process configuration will not meet the requirements because the Exception Detail is not captured for the two Business Exceptions
The Process configuration will not meet the requirements because the Exception Detail is not captured for the two Business Exceptions
If the Valid ID stage results in a 'No' answer, the Process will not throw an exception.
If the Valid ID stage results in a 'No' answer, the Process will not throw an exception.
Suggested answer: C
asked 16/09/2024
Andre Passos
35 questions

Question 14

Report
Export
Collapse

The following sub-page in a process creates an order in an order system.

Blue Prism APD01 image Question 14 20694 09162024192515000000

The Actions called perform the following steps:

Navigate to New Order - The application is navigated to a new order screen. There is a wait stage to confirm the navigation is successful - if this wait stage times out, an exception is configured which will bubble up to this page.

Enter Order Details - The Order details are entered triggering a 'Confirm Order' window. At this page, the order has not been submitted. There is a wait stage to confirm the 'Confirm Order' window has appeared - if this stage times out, an exception is configured which will bubble up to this page. Submit Order - The order is confirmed and placed in the Client's order system. There is a wait stage, for a reference number, configured that the order has been successfully submitted. If this wait stage times out, an exception is configured which will bubble up to this page. There is a known bug in the application which results in the application occasionally freezing when an order is submitted but before the reference number is displayed, thus leaving the user uncertain if the order has been successfully submitted or not.

Get Reference Number - A resultant reference number is read from the application.

In order to build some resilience into the process, some retry logic is to be added. Which of the below options offers the best retry solution?

Suggested answer: D
asked 16/09/2024
Djordje Novakovic
35 questions

Question 15

Report
Export
Collapse

Which of the following are examples of a Business Exception?

A Business Requirement states that Blue Prism should not work on any accounts with a balance greater than £1,000,000. Blue Prism has successfully read the balance field and it has returned a value of £1,100,000.
A Business Requirement states that Blue Prism should not work on any accounts with a balance greater than £1,000,000. Blue Prism has successfully read the balance field and it has returned a value of £1,100,000.
Blue Prism has detected an unexpected pop up
Blue Prism has detected an unexpected pop up
A Blue Prism wait stage has timed out waiting for a Web page to load
A Blue Prism wait stage has timed out waiting for a Web page to load
The data input to the process has been validated and failed
The data input to the process has been validated and failed
All of them
All of them
2 and 3
2 and 3
1 and 4
1 and 4
None of them
None of them
Suggested answer: D
asked 16/09/2024
Manuela Kays
36 questions

Question 16

Report
Export
Collapse

When using Control Room, which of the following statements are correct? (Choose three.)

A process can be run on multiple resources at the same time
A process can be run on multiple resources at the same time
A resource can run multiple processes at the same time
A resource can run multiple processes at the same time
Only one instance of each process can run at any one time
Only one instance of each process can run at any one time
A resource PC can only run one process at time
A resource PC can only run one process at time
A process must be published before it can be run in Control Room
A process must be published before it can be run in Control Room
Suggested answer: C, D, E
asked 16/09/2024
gregory damon
39 questions

Question 17

Report
Export
Collapse

An Insurance company has created 4 Blue Prism processes:

Change of Address

Claims Processing

Renewals

Order Letter

The Order Letter process is not a published process but is called as a sub process by each of the 3 other processes. Each day at 6am a scheduler starts:

2 instances of the Renewals process on the same virtual machine

9 instances of the Claims Processing process on 3 different virtual machines

1 instance of the Change of Address process on its own virtual machine

How many robot licenses will be consumed by the running processes?

5
5
12
12
6
6
3
3
Suggested answer: A
asked 16/09/2024
Garwin Liu
36 questions

Question 18

Report
Export
Collapse

An attempt to start a Process on resource BP0100 has resulted in the following error message:

BP0100 is too busy to run that process

Which of the below is the most likely cause of this error?

Resource BP0100 is offline
Resource BP0100 is offline
There is more than one instance of the Blue Prism resourcepc command running on resource BP0100
There is more than one instance of the Blue Prism resourcepc command running on resource BP0100
The BPServer service is not running on the Blue Prism Application Server
The BPServer service is not running on the Blue Prism Application Server
A Process is running on resource BP0100 that calls a Business Object with a run mode of 'Exclusive'
A Process is running on resource BP0100 that calls a Business Object with a run mode of 'Exclusive'
Suggested answer: B
asked 16/09/2024
Marcin Piotrowski
40 questions

Question 19

Report
Export
Collapse

A retail bank has promoted 5 Blue Prism processes to production:

Email Poller

Customer Onboarding

Amend Contact Details

Direct Debit Cancellations Onboarding Reporting

One instance of the email Poller process will run 24/7 feeding work queues for the other two processes. Two concurrent instances of the Customer Onboarding process will run between 6am and 11pm each day on the same VM. Two concurrent instances of the Amend Contact Details process will run between 8am and 8pm each day on two VMs. One instance of the Direct Debit Cancellations process will run between 6am and 4pm each day on the same VM as the Email Poller process. The scheduler that starts the Direct Debit Cancellations process is configured to run the Onboarding Reporting process when the Direct Debit Cancellations process has successfully completed.

How many robot licenses are required?

A3

B4

C5

D6

Suggested answer:
asked 16/09/2024
Sasha Grib
44 questions

Question 20

Report
Export
Collapse

Study the process flow below:

Blue Prism APD01 image Question 20 20700 09162024192515000000

Blue Prism APD01 image Question 20 20700 09162024192515000000

Blue Prism APD01 image Question 20 20700 09162024192515000000

Blue Prism APD01 image Question 20 20700 09162024192515000000

Blue Prism APD01 image Question 20 20700 09162024192515000000

The initial values for the Loop Count and Max Loop data items are 0 and 5 respectively.

How many times will the Business Objects Action ‘Screen AO1 – Enter Data’ be read into memory during the execution of the Process?

4
4
5
5
1
1
0
0
Suggested answer: C
asked 16/09/2024
miquel martin leiva
42 questions
Total 51 questions
Go to page: of 6