ExamGecko
Home / ISC / CAP / List of questions
Ask Question

ISC CAP Practice Test - Questions Answers, Page 6

Add to Whishlist

List of questions

Question 51

Report Export Collapse

In which of the following phases of the DITSCAP process does Security Test and Evaluation (ST&E) occur?

Phase 2
Phase 2
Phase 3
Phase 3
Phase 1
Phase 1
Phase 4
Phase 4
Suggested answer: B
asked 18/09/2024
sergio sombrero
40 questions

Question 52

Report Export Collapse

You are the project manager of the NHH project for your company. You have completed the first round of risk management planning and have created four outputs of the risk response planning process. Which one of the following is NOT an output of the risk response planning?

Risk-related contract decisions
Risk-related contract decisions
Project document updates
Project document updates
Risk register updates
Risk register updates
Organizational process assets updates
Organizational process assets updates
Suggested answer: D
asked 18/09/2024
Hariett Mambo
48 questions

Question 53

Report Export Collapse

Thomas is a key stakeholder in your project. Thomas has requested several changes to the project scope for the project you are managing. Upon review of the proposed changes, you have discovered that these new requirements are laden with risks and you recommend to the change control board that the changes be excluded from the project scope. The change control board agrees with you. What component of the change control system communicates the approval or denial of a proposed change request?

Configuration management system
Configuration management system
Change log
Change log
Scope change control system
Scope change control system
Integrated change control
Integrated change control
Suggested answer: D
asked 18/09/2024
Larry Wong
36 questions

Question 54

Report Export Collapse

Which of the following assessment methodologies defines a six-step technical security evaluation?

OCTAVE
OCTAVE
FITSAF
FITSAF
DITSCAP
DITSCAP
FIPS 102
FIPS 102
Suggested answer: D
asked 18/09/2024
Jesse Serrano
40 questions

Question 55

Report Export Collapse

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?

1.06
1.06
0.92
0.92
-$37,800
-$37,800
0.93
0.93
Suggested answer: B
asked 18/09/2024
Maher Khamessi
33 questions

Question 56

Report Export Collapse

A Web-based credit card company had collected financial and personal details of Mark before issuing him a credit card. The company has now provided Mark's financial and personal details to another company. Which of the following Internet laws has the credit card issuing company violated?

Security law
Security law
Privacy law
Privacy law
Copyright law
Copyright law
Trademark law
Trademark law
Suggested answer: B
asked 18/09/2024
Ryan John Ricafranca
54 questions

Question 57

Report Export Collapse

Which of the following is a 1996 United States federal law, designed to improve the way the federal government acquires, uses, and disposes information technology?

Computer Misuse Act
Computer Misuse Act
Lanham Act
Lanham Act
Clinger-Cohen Act
Clinger-Cohen Act
Paperwork Reduction Act
Paperwork Reduction Act
Suggested answer: C
asked 18/09/2024
SERGIO MELOSEVICH
50 questions

Question 58

Report Export Collapse

Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the following statements best defines what quantitative risk analysis will review?

The quantitative risk analysis seeks to determine the true cost of each identified risk event and the probability of each risk event to determine the risk exposure.
The quantitative risk analysis seeks to determine the true cost of each identified risk event and the probability of each risk event to determine the risk exposure.
The quantitative risk analysis process will review risk events for their probability and impact on the project objectives.
The quantitative risk analysis process will review risk events for their probability and impact on the project objectives.
The quantitative risk analysis reviews the results of risk identification and prepares the project for risk response management.
The quantitative risk analysis reviews the results of risk identification and prepares the project for risk response management.
The quantitative risk analysis process will analyze the effect of risk events that may substantially impact the project's competing demands.
The quantitative risk analysis process will analyze the effect of risk events that may substantially impact the project's competing demands.
Suggested answer: D
asked 18/09/2024
Djordje Novakovic
44 questions

Question 59

Report Export Collapse

Which of the following is used to indicate that the software has met a defined quality level and is ready for mass distribution either by electronic means or by physical media?

RTM
RTM
CRO
CRO
DAA
DAA
ATM
ATM
Suggested answer: A
asked 18/09/2024
Matthew Sain
41 questions

Question 60

Report Export Collapse

Amy is the project manager for her company. In her current project the organization has a very low tolerance for risk events that will affect the project schedule.

Management has asked Amy to consider the affect of all the risks on the project schedule. What approach can Amy take to create a bias against risks that will affect the schedule of the project?

She can have the project team pad their time estimates to alleviate delays in the project schedule.
She can have the project team pad their time estimates to alleviate delays in the project schedule.
She can create an overall project rating scheme to reflect the bias towards risks that affect the project schedule.
She can create an overall project rating scheme to reflect the bias towards risks that affect the project schedule.
She can filter all risks based on their affect on schedule versus other project objectives.
She can filter all risks based on their affect on schedule versus other project objectives.
She can shift risk-laden activities that affect the project schedule from the critical path as much as possible.
She can shift risk-laden activities that affect the project schedule from the critical path as much as possible.
Suggested answer: B
asked 18/09/2024
Abraham Ermann
46 questions
Total 395 questions
Go to page: of 40
Search

Related questions