ExamGecko
Home / ISC / CISSP-ISSMP / List of questions
Ask Question

ISC CISSP-ISSMP Practice Test - Questions Answers, Page 11

List of questions

Question 101

Report Export Collapse

Which of the following recovery plans includes specific strategies and actions to deal with specific variances to assumptions resulting in a particular security problem, emergency, or state of affairs?

Disaster recovery plan
Disaster recovery plan
Contingency plan
Contingency plan
Continuity of Operations Plan
Continuity of Operations Plan
Business continuity plan
Business continuity plan
Suggested answer: B
asked 18/09/2024
Tuukka Valkeasuo
39 questions

Question 102

Report Export Collapse

Which of the following BCP teams handles financial arrangement, public relations, and media inquiries in the time of disaster recovery?

Software team
Software team
Off-site storage team
Off-site storage team
Applications team
Applications team
Emergency-management team
Emergency-management team
Suggested answer: D
asked 18/09/2024
HAO KANG SUNG
41 questions

Question 103

Report Export Collapse

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

Yes, the ZAS Corporation did not choose to terminate the contract work.
Yes, the ZAS Corporation did not choose to terminate the contract work.
It depends on what the outcome of a lawsuit will determine.
It depends on what the outcome of a lawsuit will determine.
It depends on what the termination clause of the contract stipulates.
It depends on what the termination clause of the contract stipulates.
No, the ZAS Corporation did not complete all of the work.
No, the ZAS Corporation did not complete all of the work.
Suggested answer: C
asked 18/09/2024
Danilo Ferrareis
41 questions

Question 104

Report Export Collapse

Which of the following are the goals of risk management? Each correct answer represents a complete solution. Choose three.

Assessing the impact of potential threats
Assessing the impact of potential threats
Identifying the accused
Identifying the accused
Finding an economic balance between the impact of the risk and the cost of the countermeasure
Finding an economic balance between the impact of the risk and the cost of the countermeasure
Identifying the risk
Identifying the risk
Suggested answer: A, C, D
asked 18/09/2024
gayathri devi
43 questions

Question 105

Report Export Collapse

You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

Quantitative risk analysis
Quantitative risk analysis
Qualitative risk analysis
Qualitative risk analysis
Requested changes
Requested changes
Risk audits
Risk audits
Suggested answer: C
asked 18/09/2024
Francesco Balducci
40 questions

Question 106

Report Export Collapse

Della works as a security manager for SoftTech Inc. She is training some of the newly recruited personnel in the field of security management. She is giving a tutorial on DRP. She explains that the major goal of a disaster recovery plan is to provide an organized way to make decisions if a disruptive event occurs and asks for the other objectives of the DRP. If you are among some of the newly recruited personnel in SoftTech Inc, what will be your answer for her question?

Each correct answer represents a part of the solution. Choose three.

Protect an organization from major computer services failure.
Protect an organization from major computer services failure.
Minimize the risk to the organization from delays in providing services.
Minimize the risk to the organization from delays in providing services.
Guarantee the reliability of standby systems through testing and simulation.
Guarantee the reliability of standby systems through testing and simulation.
Maximize the decision-making required by personnel during a disaster.
Maximize the decision-making required by personnel during a disaster.
Suggested answer: A, B, C
asked 18/09/2024
Tim Dekker
47 questions

Question 107

Report Export Collapse

SIMULATION

Fill in the blank with an appropriate phrase.______________ is used to provide security mechanisms for the storage, processing, and transfer of data.

Data classification
Data classification
Suggested answer: A
asked 18/09/2024
Nqobile Nxumalo
46 questions

Question 108

Report Export Collapse

Software Development Life Cycle (SDLC) is a logical process used by programmers to develop software. Which of the following SDLC phases meets the audit objectives defined below: System and data are validated. System meets all user requirements. System meets all control requirements.

Programming and training
Programming and training
Evaluation and acceptance
Evaluation and acceptance
Definition
Definition
Initiation
Initiation
Suggested answer: B
asked 18/09/2024
Mariusz Lewandowski
47 questions

Question 109

Report Export Collapse

You are the project manager of the NGQQ Project for your company. To help you communicate project status to your stakeholders, you are going to create a stakeholder register. All of the following information should be included in the stakeholder register except for which one?

Become a Premium Member for full access
  Unlock Premium Member

Question 110

Report Export Collapse

Which of the following are examples of physical controls used to prevent unauthorized access to sensitive materials?

Become a Premium Member for full access
  Unlock Premium Member
Total 218 questions
Go to page: of 22
Search

Related questions