ISC CISSP-ISSMP Practice Test - Questions Answers, Page 3
List of questions
Related questions
Which of the following laws is the first to implement penalties for the creator of viruses, worms, and other types of malicious code that causes harm to the computer systems?
SIMULATION Fill in the blank with an appropriate phrase.________ models address specifications, requirements, and design, verification and validation, and maintenance activities.
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:
How much capital should the project set aside for the risk contingency reserve?
Which of the following statements about system hardening are true? Each correct answer represents a complete solution. Choose two.
Which of the following are the common roles with regard to data in an information classification program? Each correct answer represents a complete solution.
Choose all that apply.
Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project."
Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?
You are the project manager of the HJK Project for your organization. You and the project team have created risk responses for many of the risk events in the project. Where should you document the proposed responses and the current status of all identified risks?
Which of the following security controls will you use for the deployment phase of the SDLC to build secure software? Each correct answer represents a complete solution. Choose all that apply.
Which of the following can be prevented by an organization using job rotation and separation of duties policies?
Question