Question 1 / 40
Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once. What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier?
Note: There are 2 correct answers to this question.
Set a maximum lot size in the quota arrangement item and select the 1x checkbox
Assign a rounding profile in the material master record of the planned material
Assign the indicator for quota splitting to the lot-sizing procedure being used
Set a maximum quola quantity in the quota arrangement item for each supplier