During which of the principal performance testing activities are the building blocks for larger, more complex tests created?

During test completion

During test completion

During test planning

During test planning

During test design

During test design

During test implementation

During test implementation

Comment (0)
Suggested answer: D
Explanation:

Test implementation is the stage where smaller test components are created and assembled into larger test scenarios. This phase includes scripting, test data preparation, and configuring load profiles.

Option A (Test completion) involves analyzing results, not building tests.

Option B (Test planning) focuses on strategies and objectives, not test creation.

Option C (Test design) defines test scenarios and cases, but the actual building happens in implementation.