A company plans to implement Dynamics 365 Supply Chain Management.

The company wants shop floor workers to register their daily work by using the production floor execution interface.

Which two activities can employees perform by using the tool? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Schedule a production order.

Schedule a production order.

Register scrap quantity during production.

Register scrap quantity during production.

Register raw material consumption.

Register raw material consumption.

Clock in and clock out.

Clock in and clock out.

Comment (0)
Suggested answer: B, D
Explanation:


Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/production-floor-execution-configure

https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/production-floor-execution-use