A company wants to account for the time to set up a machine to manufacture a new part.

You need to set up the costing calculations in the system.

Which three calculation group warnings can you set up? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

A.

No consumption

Answers
A.

No consumption

B.

No cost price

Answers
B.

No cost price

C.

No BOM

Answers
C.

No BOM

D.

No resources

Answers
D.

No resources

E.

No route

Answers
E.

No route

Suggested answer: B, C, E

Explanation:

Reference: https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/bom-calculation-groups