A company wants to account for the time to set up a machine to manufacture a new part.
You need to set up the costing calculations in the system.
Which three calculation group warnings can you set up? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.
A.
No consumption
B.
No cost price
C.
No BOM
D.
No resources
E.
No route