Question 3 - MB-320 discussion
Note: This question-is part of a series of questions that present the same scenario. Each question-in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question-in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.
You need to create a subcontracting activity for the painting service.
Solution:
Create a vendor resource and work cell for outsourced painting; add the vendor resource to the work cell.
Create a production flow process activity using the painting work cell and the service item for picking.
When the service is required, create a purchase order to the subcontracting vendor and add a line for the service item and the vendor price.
Does the solution meet the goal?
Yes
No