You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.
The item has the following Lean setup:
The setup uses a Lean schedule group with a throughput ratio = 2.
The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.
The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day).
The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item's production flow activity.
What should you do?
Create a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 0.0167 (e.g. 1 hour/60 minutes)
Create a route with a runtime = 1, a process quantity = 10, and the operation's hours/time = 1
Create a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 1
Create a route with a runtime = 1, a process quantity = 1, and the operation's hours/time = 1