Question 161 - MB-320 discussion

Report
Export

You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.

The item has the following Lean setup:

The setup uses a Lean schedule group with a throughput ratio = 2.

The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.

The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day).

The throughput is 10 per hour.

You need to set up a Discrete operation to mirror the item's production flow activity.

What should you do?

A.

Create a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 0.0167 (e.g. 1 hour/60 minutes)

Answers
A.

Create a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 0.0167 (e.g. 1 hour/60 minutes)

B.

Create a route with a runtime = 1, a process quantity = 10, and the operation's hours/time = 1

Answers
B.

Create a route with a runtime = 1, a process quantity = 10, and the operation's hours/time = 1

C.

Create a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 1

Answers
C.

Create a route with a runtime = 1, a process quantity = 6, and the operation's hours/time = 1

D.

Create a route with a runtime = 1, a process quantity = 1, and the operation's hours/time = 1

Answers
D.

Create a route with a runtime = 1, a process quantity = 1, and the operation's hours/time = 1

Suggested answer: B

Explanation:

Reference: https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-schedule- groups