Note: This question-is part of a series of questions that present the same scenario. Each question-in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solutions, while others might not have a correct solution.

After you answer a question-in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

A manufacturing plant uses Lean process. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service.

You need to create a subcontracting activity for the painting service.

Solution:

* Create a purchase agreement for the subcontracting vendor that contains the pricing information for SP-01.

* Create a vendor resource and a work cell for outsourced painting, then add the resource to the work cell.

* Create a production flow process activity using the painting work cell and the service item as the picking activity.

* Create a service term on the activity to tie the purchase agreement to the activity.

Does the solution meet the goal?


A.

Yes

Answers
A.

Yes

B.

No

Answers
B.

No

Suggested answer: A

Explanation:

References: https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/activity-based-subcontracting