List of questions
Related questions
Question 19 - MB-320 discussion
You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.
The item has the following Lean setup:
The setup uses a Lean schedule group with a throughput ratio=2
The process activity tied to production flow has the following runtime activity times: time=3 min, per quantity=1
The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8-hour day)
The throughput is 10 per hour
You need to set up a Discrete operation to mirror the item's production flow activity.
What should you do?
Create a route with a runtime =1, a process quantity =6, and the operation's hours/time =1
Create a route with a runtime =1, a process quantity =10, and the operation's hours/time =1
Create a route with a runtime =6, a process quantity =1, and the operation's hours/time =1
Create a route with a runtime =10, a process quantity =6, and the operation's hours/time =1
0 comments
Leave a comment first