You are a production manager at a company which produces large batches of coffee and creamers.

After a quality inspection, batch 120008 of your cold brew coffee (item number CB-0001) was found to be too acidic and must be reworked.

You need to add 20 grams of sugar and stir the product for an additional 0.5 hours.

What three actions are required on the rework order? Each correct answer presents part of the solution.

NOTE: Each correct selection is worth one point.

A.

Delete all items from the production formula except for 20 grams of sugar

Answers
A.

Delete all items from the production formula except for 20 grams of sugar

B.

Add 20 grams of sugar to the production formula

Answers
B.

Add 20 grams of sugar to the production formula

C.

Delete all route operations except for a half an hour stirring operation

Answers
C.

Delete all route operations except for a half an hour stirring operation

D.

Manually reserve batch 120008 after estimating the batch order

Answers
D.

Manually reserve batch 120008 after estimating the batch order

E.

Add a route operation for 0.5 run time hours of stirring

Answers
E.

Add a route operation for 0.5 run time hours of stirring

Suggested answer: B, D, E

Explanation:

Reference:

https://technologyblog.rsmus.com/microsoft-dynamics/dynamics-365-for-finance-and-operations/rework-batch-orders-in-microsoft-dynamics-365-for-finance-and-operationscmpidblogtmc-ms-dynamics-1219d01/

asked 05/10/2024
Maris Romans
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first