Question 45 - MB-320 discussion
A paint manufacturer is using Process manufacturing. The manufacturer has a quality error. Batches of paint that use the wrong formula have been marked for rework.
The production planner reports they cannot schedule the batch order even though the order has been estimated.
You need to add reservations to the items to be used for the rework order.
What should you do?
A.
Reserve the inventory in the formula
B.
Reset the batch order and delete the formula items. Re-enter the formula items
C.
Add by-products that need to be used and then re-estimate
D.
Add co-products that need to be used and then re-estimate
Your answer: