A vendor plans to supply replacements for a product that they manufactured.

The cost associated with manufacturing most components of the replacement product differ from costs associated with the original product.

You need to plan for the new cost of the item in determining the sales price.

Which costing version explosion mode should you use?

A.

According to BOM line type

Answers
A.

According to BOM line type

B.

Multilevel

Answers
B.

Multilevel

C.

Single level

Answers
C.

Single level

D.

Make to Order

Answers
D.

Make to Order

Suggested answer: B

Explanation:

Reference:

https://docs.microsoft.com/en-us/dynamics365/supply-chain/cost-management/simulate-cost-changes-costing-version- planned-costs