DRAG DROP

A manufacturing company uses Dynamics 365 Supply Chain Management The company operates three eight-hour shifts per day, Monday through Friday.

The company purchased equipment for a new process that cannot be performed with existing equipment. This specialized equipment performs only this unique task. The machinery must always be monitored and controlled by a worker.

The machine must be added to the existing production line and be ready as soon as possible. Future planned production orders must not overload the running maximums of the new machine.

You need to configure the system.

Which four actions must you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Question 193
Correct answer: Question 193

Explanation:

Add the machine as a resource..

Create a capability for the...

Assign the machine resouce...

Assign a working time calendar to the resource.