List of questions
Related questions
Question 199 - MB-320 discussion
A company configures master planning to order large and expensive aluminum sheets that are only available at certain times of the year.
The warehouse manager reports that replenishment levels are too high, causing inventory value to be over budget. In addition, the aluminum sheets take up too much space on the shop floor.
You need to configure the appropriate replenishment method.
Which coverage dimension should you use?
A.
Per period
B.
Per requirement
C.
Min/Max
D.
Manual
Your answer: