You want to create a single-cycle plan with a cycle of 12 months. You use the scheduling indicator Time-key date. The orders should be called 3 months before the planned date.How can you set up the maintenance plan? Note: There are 2 correct answers to this question

A.

Set the call horizon to 25%.

Answers
A.

Set the call horizon to 25%.

B.

Set the call horizon to 75%

Answers
B.

Set the call horizon to 75%

C.

Set the offset to 3 months

Answers
C.

Set the offset to 3 months

D.

Set the call horizon to 90 days.

Answers
D.

Set the call horizon to 90 days.

Suggested answer: B, D