ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 10 - C_THR84_2405 discussion

Report
Export

What are the recommended actions to be completed before the Career Site Builder (CSB) kickoff call?Note: There are 2 correct answers to this question.

A.

Assist the customer to complete the Readiness Checklist.

Answers
A.

Assist the customer to complete the Readiness Checklist.

B.

Review the statement of work (SOW).

Answers
B.

Review the statement of work (SOW).

C.

Develop the CSB project plan.

Answers
C.

Develop the CSB project plan.

D.

Finish the CSB Configuration Workbook.

Answers
D.

Finish the CSB Configuration Workbook.

Suggested answer: A, B

Explanation:

According to the SAP SuccessFactors Recruiting: Candidate Experience Administration course1, before the CSB kickoff call, the following actions are recommended:

Assist the customer to complete the Readiness Checklist. This checklist helps the customer to prepare for the CSB implementation by gathering the necessary information and assets, such as logos, images, videos, etc.

Review the statement of work (SOW). This document defines the scope, deliverables, timeline, and responsibilities of the CSB project. It is important to review the SOW to ensure that the customer's expectations and requirements are aligned with the project plan and budget.

Developing the CSB project plan and finishing the CSB Configuration Workbook are not recommended actions before the CSB kickoff call. These tasks are usually done after the kickoff call, as part of the CSB implementation process.Reference:SAP Certified Application Associate - SAP SuccessFactors Recruiting: Candidate Experience 2H/2023,SAP SuccessFactors Recruiting: Candidate Experience Administration

asked 31/10/2024
Mustafa Hussien
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first