Which of the following approaches should first be considered as part of process improvement?

A.
Hiring more skilled people to perform the job
Answers
A.
Hiring more skilled people to perform the job
B.
Making better use of existing resources
Answers
B.
Making better use of existing resources
C.
Buying better and faster equipment
Answers
C.
Buying better and faster equipment
D.
Applying stricter quality control
Answers
D.
Applying stricter quality control
Suggested answer: B

Explanation:

Process improvement is a method of analyzing and enhancing the production methods and techniques to increase productivity and performance. Process improvement aims to reduce costs, waste, defects, and errors, as well as to improve quality, efficiency, and customer satisfaction. When considering process improvement, the first approach that should be considered is making better use of existing resources. This means that the production system should optimize the utilization and allocation of the available resources, such as materials, labor, machines, and space. This can be achieved by implementing various techniques, such as lean manufacturing, six sigma, kaizen, or 5S. Making better use of existing resources can help to improve the process without requiring additional investment or expenditure.

The other options are not the first approaches that should be considered as part of process improvement. Hiring more skilled people to perform the job is not the first approach, as it may increase the labor cost and require more training and supervision. Hiring more skilled people may not necessarily improve the process if the existing methods and techniques are inefficient or ineffective. Buying better and faster equipment is not the first approach, as it may involve a large capital outlay and a long payback period. Buying better and faster equipment may not necessarily improve the process if the existing resources are underutilized or misallocated. Applying stricter quality control is not the first approach, as it may increase the inspection and testing cost and time. Applying stricter quality control may not necessarily improve the process if the existing methods and techniques are prone to errors or defects.Reference: CPIM Exam Content Manual Version 7.0, Domain 8: Manage Quality, Continuous Improvement, and Technology, Section 8.2: Continuous Improvement Concepts, p. 46; Process Improvement; Process Improvement Definition.

asked 16/09/2024
Rahul Biradavolu
41 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first