Question 146 - CPIM-Part-2 discussion
Which of the following planning modules considers the longest-range planning goals?
A.
Capacity requirements planning (CRP)
B.
Input/output analysis
C.
Resource planning
D.
Rough-cut capacity planning (RCCP)