A master production schedule serves a company best by functioning as a:

A.
dispatch list.
Answers
A.
dispatch list.
B.
forecast system buffer.
Answers
B.
forecast system buffer.
C.
priority planning tool.
Answers
C.
priority planning tool.
D.
supplier scheduling system.
Answers
D.
supplier scheduling system.
Suggested answer: C

Explanation:

A Master Production Schedule (MPS) serves as a priority planning tool by:

Scheduling Production: It details what products need to be produced, in what quantities, and when, ensuring that customer demand is met efficiently.

Balancing Demand and Supply: The MPS takes into account available capacity, inventory levels, and lead times to balance supply with forecasted demand.

Resource Allocation: It helps in planning the use of resources, such as labor, machinery, and materials, ensuring that production processes are optimized.

Order Management: The MPS provides a timeline for when orders will be fulfilled, helping manage customer expectations and improving service levels.

APICS, 'Basics of Supply Chain Management'

'Manufacturing Planning and Control Systems for Supply Chain Management' by Thomas E. Vollmann, William L. Berry, and D. Clay Whybark

asked 16/09/2024
jordi vanderpooten
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first