Question 48 - BAPv5 discussion

Report
Export

A Business Analyst is reviewing the stakeholder management strategy for a high profile I Human Resources (HR) protect.

Following an organizational restructure, Harvey's role has changed from Director of Operations to Director of HR and he has Inherited sponsorship of the project. Harvey was previously involved in the project, but had little interest because his focus was on the Operational Projects that he sponsored.

Which of the following sets of stakeholder management strategies represent appropriate approaches for Harvey; firstly for when the project started and secondly now that his role has changed?

A.
Keep watch; Constant active management
Answers
A.
Keep watch; Constant active management
B.
Ignore; Constant active management
Answers
B.
Ignore; Constant active management
C.
Keep on side; Constant active management
Answers
C.
Keep on side; Constant active management
D.
Ignore; Keep informed. The stakeholder management strategy depends on the power and interest of the stakeholder in the project. Harvey's role has changed from Director of Operations to Director of HR, which means his power and interest in the HR project have also changed. When he was Director of Operations, he had low power and low interest in the HR project, so he could be ignored as a stakeholder. Now that he is Director of HR and the sponsor of the project, he has high power and high interest in the project, so he needs constant active management as a stakeholder. Option B is the correct answer.
Answers
D.
Ignore; Keep informed. The stakeholder management strategy depends on the power and interest of the stakeholder in the project. Harvey's role has changed from Director of Operations to Director of HR, which means his power and interest in the HR project have also changed. When he was Director of Operations, he had low power and low interest in the HR project, so he could be ignored as a stakeholder. Now that he is Director of HR and the sponsor of the project, he has high power and high interest in the project, so he needs constant active management as a stakeholder. Option B is the correct answer.
Suggested answer: B

Explanation:

Stakeholder Analysis using the Power Interest Grid - ProjectManagement.com

Power Interest Grid: How to Use, Benefits, Examples - KnowledgeHut

asked 16/09/2024
Tanya Resto
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first