DRAG DROP

What is the sequence of steps to install an XE9680 server in a new rack.



Question 2
Correct answer: Question 2

Explanation:

Unpack the server from the shipping packaging.

Install the rail assembly.

Transport the server and align with the rack.

Slide the server into the rack.

Connect the power and network cables.

Power on the server.

Dell EMC PowerEdge XE9680 Installation and Service Manual: This manual provides detailed step-by-step instructions on unpacking, installing, and powering on the server.

Dell EMC Technical Specifications Guide: Offers comprehensive details on the hardware specifications and installation procedures for Dell PowerEdge servers.


Dell EMC PowerEdge XE9680 Installation and Service Manual: This manual provides detailed step-by-step instructions on unpacking, installing, and powering on the server.

Dell EMC Technical Specifications Guide: Offers comprehensive details on the hardware specifications and installation procedures for Dell PowerEdge servers.