The budgeted cost of work performed is a metric best used to measure which project management activity?

A.
Resource planning.
Answers
A.
Resource planning.
B.
Cost estimating
Answers
B.
Cost estimating
C.
Cost budgeting.
Answers
C.
Cost budgeting.
D.
Cost control.
Answers
D.
Cost control.
Suggested answer: D