According to UA guidance on IT, at which of the following stages of the project life cycle would the project manager most likely address the need to coordinate project resources?

A.
Initiation.
Answers
A.
Initiation.
B.
Planning.
Answers
B.
Planning.
C.
Execution.
Answers
C.
Execution.
D.
Monitoring.
Answers
D.
Monitoring.
Suggested answer: B