A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?

A.
Quality control checklist
Answers
A.
Quality control checklist
B.
Communication plan
Answers
B.
Communication plan
C.
Decision analysis
Answers
C.
Decision analysis
D.
Risk review
Answers
D.
Risk review
Suggested answer: A