The product backlog refinement meeting for a project is complete but two stakeholders do not agree on the priority of several product backlog items. What should the business analyst (BA) do to help move the project forward?

A.
Schedule a backlog walkthrough with the two stakeholders
Answers
A.
Schedule a backlog walkthrough with the two stakeholders
B.
Confirm the authority of the two stakeholders
Answers
B.
Confirm the authority of the two stakeholders
C.
Notify the project manager
Answers
C.
Notify the project manager
D.
Apply the previous backlog priority
Answers
D.
Apply the previous backlog priority
Suggested answer: A