Question 477 - CCBA discussion

Report
Export

A business owner has identified a high priority requirement that needs to be implemented immediately. The project manager has asked the business analyst (BA) to perform an impact analysis of this change. Which factor will the BA need to consider?

A.
Number of systems being affected by the requirement
Answers
A.
Number of systems being affected by the requirement
B.
Original source of the requirement
Answers
B.
Original source of the requirement
C.
Method of requirement communication
Answers
C.
Method of requirement communication
D.
Selection of the elicitation for the requirement
Answers
D.
Selection of the elicitation for the requirement
Suggested answer: A