Question 478 - CCBA discussion
A business analyst (BA) is working on a project to improve product delivery. The issues arise during the latter stages of the delivery Freecycle and are due to poor communication of the business analysis information from the elicitation phase. As a result, a BA has ensured that the testing and training teams are identified as stakeholders on the RACI Matrix going forward. To which RAG designation should the training and testing teams be added?
A.
Consulted
B.
Responsible
C.
Accountable
D.
Informed