A change to support a regulatory requirement is proposed for inclusion in the scope of a project. A business analyst (BA) conducts an impact analysis to determine the extent of the change. What previous task could assist the BA in performing the impact analysis?

A.
Update use case scenarios
Answers
A.
Update use case scenarios
B.
Perform a risk analysis
Answers
B.
Perform a risk analysis
C.
Create requirement relationships
Answers
C.
Create requirement relationships
D.
Conduct a cost-benefit analysis
Answers
D.
Conduct a cost-benefit analysis
Suggested answer: C